Facelift of three major ports on Lake Victoria set to close next September

By Wilhelm Mulinda , The Guardian
Published at 08:30 AM Sep 06 2024
Lake Victoria Port
Photo: Guardian Correspondent
Lake Victoria Port

THE expansion of three main ports on Lake Victoria is now scheduled to be completed by 15th September next year after reaching various stages of progress, it has been confirmed.

Speaking to journalists here yesterday, Erasto Lugenge, manager for Lake Victoria ports, reported that as of yesterday, Mwanza North Port was at 38.8 percent, Kemondo was 73 percent and Bukoba 63 percent.

Lugenge noted that according to the contract, the extension work at Mwanza North Port is set to be completed by 3rd November this year, at Kemondo by 28th September, and at Bukoba by 9th September.

He attributed the delays to changes in the design of MV Mwanza Hapa Kazi TU! which also required modifications to fit the designs at the ports.

The extension work, which began on 3rd May this year, aims to provide sufficient space for the MV Mwanza Hapa Kazi TU! to dock at the ports.

Lugenge mentioned that the vessel is expected to dock at Mwanza North Port starting November. He emphasised that the government through Tanzania Ports Authority (TPA), is committed to ensuring timely completion of the strategic projects to drive development.

“People should be patient during this period of port infrastructure improvement as they will benefit more in terms of transport and business once the work is complete,” he said.